Two-Phase Paving Method for Quality Driveways

At Dependable Paving Co., we use a two-phase method for driveway installation that our owner developed decades ago. This method ensures the construction of a heavy-built crushed-stone foundation with the binder layer of asphalt installed in Phase I, and the installation of the top coat in Phase II. Our two-phase process focuses on full depth excavation, thick layers of stone and asphalt, and using quality materials throughout the build to give you an asphalt surface that will last for decades.


For an in-depth look at our two-phase paving process that will give you a full understanding of how to properly build a driveway, click the button below.

Two-Phase Paving Process

Paving Phase I - New Sub-Base And The Binder Layer Of Asphalt

  • The area is excavated to 12″ below the finished grade.
  • Geo-Textile fabric is installed over the sub-soil to prevent tire ruts.
  • 10″ of runner crush stone is installed, and then power rolled.
  • 8" of minus-4 runnercrush.
  • 2" of regular runnercrush.
  • 3″ of binder hot-mix asphalt is installed and power rolled.
  • The entire area is cleaned and barricaded.
  • Newly paved area can be trafficked in 3-5 days.

Paving Phase II - The Top Coat

The following year, Phase II is installed.

  • Grass edges will be trimmed.
  • Pavement will be cleaned of existing debris.
  • Low areas will be shimmed and compacted
  • 1.5" of hot-mix Armor Coat topping will be installed and power rolled.
  • The entire area is cleaned and barricaded.
  • Newly paved area can be trafficked in 2-3 days.

Driveway Resurface

  • Grass edges will be trimmed.
  • Pavement will be cleaned of existing debris.
  • Low areas will be shimmed and compacted
  • 2" of hot-mix Armor Coat topping will be installed and power rolled.
  • The entire area is cleaned and barricaded.
  • Newly paved area can be trafficked in 2-3 days.